  1. 01Your invitation
  2. 02Reading the board
  3. 03What each section answers
  4. 04Project budget
  5. 05The reliability score
  6. 06Quick reference
Portfolio Control Center
by BI DEVELOPMENT
Project portfolio management

Portfolio Control Center

Guest manual
For the Guest
Reads the published reports and month photos. Chooses the reporting date and the months in view.
Guest manual · Version 2.0 · for Portfolio Control Center V1
October 2026
Portfolio Control Center
by BI Development
Portfolio Control Center · Guest manual
Guest

Your invitation

Your organisation's Manager gives you access to read its Portfolio Control Center: the state of the project portfolio, report by report. Nothing you do changes the data. It runs inside Microsoft Teams, with your work account.

From the link to the board
1
Open the invitation e-mail
It comes from support@bidevelopment.ro and names who invited you. Select Open in Teams. Nothing arrived? Your Manager sends it again or sends you the link.
2
Open it in Teams
Or, in Teams, Apps › search Portfolio Control Center. Desktop, web or mobile, it works the same.
3
Sign in with your work account
The first time, Teams asks you to confirm it. There is no separate password.
4
Confirm
The page reads “<who> gives you access to <organisation> as Guest.” Select Confirm, or Decline. From then on the access is bound to this account.
5
Read the board
It opens there every time, on the latest report. Until the Manager publishes one: “No report has been published yet. The Manager publishes one from the Management board.”
If you are from another organisation

You keep your own Microsoft 365 account: no guest account, no Microsoft guest e-mail. At the top of the page, Organisation lists your own and those that invited you. A waiting invitation reads “<organisation> invited you.” Open it, then Confirm.

If it does not open
You see
Most likely
Ask
Your Manager has not given you access yet.
No access on this account, or the invitation went to another address
The Manager
Need admin approval
Sign-in to the app is not approved in your organisation
Your Microsoft 365 administrator
Anything else
—
support@bidevelopment.ro
Portfolio Control Center by BI Development
02 / 07
Contents ↑
Portfolio Control Center · Guest manual
The board

Reading the board

The board opens on the latest report. Everything at the top of the page is a way in; nothing you click changes the data. Beside each chart, ? shows how it is worked out, step by step, and the speaker reads it out; presenting in a Teams meeting, share with Include sound so the others hear it. Under the title, your organisation's logo, if the Manager has set one.

Your organisation · Projects
Portfolio Control Center
1
Reporting date
latest report ▾
2
Window
from ▾
–
to ▾
3
%
4
01 Capacity
02 Register
03 Budget
04 Timeline
05 Composition
5
Portfolio
Effort
Method
1
Reporting date
The board opens on the latest report: one the Manager published, or a month photo, “October 2026 · month closed”. Pick another and the board redraws exactly as it was, with the parameters it was computed with. The Manager and the Team Leads also see Today, not published.
2
Window
The months in view. The board opens on the Manager's window, by default 3 months before the reporting month and 9 after. Choose any other range for your session; Back to the default window restores it.
3
Overall reliability
How far the data underneath can be trusted, against the line to clear set by the Manager (90% by default). It is about the data, not about project performance.
4
Section cards
One per section the Manager shows. A red edge means needs attention. Hover for the figure and the reason; click to go straight there.
5
Three tabs
Portfolio: plan, estimates, budget, timeline. Effort: what was actually consumed. Method: how every figure is calculated.
Everywhere on the board: hover a figure, a cell or a column heading for the detail behind it. Each team's panel opens and closes with a click. A figure with nothing under it reads —.
Portfolio Control Center by BI Development
03 / 07
Contents ↑
Portfolio Control Center · Guest manual
The board

What each section answers

Portfolio tab · the plan
01
Capacity
Is each team over-committed, month by month? One band per team, closed, with its peak; the arrow opens the months. A heatmap per person.
02
Project register
Where does each project stand? Filter by location, status or team; sort any column.
03
Budget
How much of each approved budget is spent, set against completion, and month by month against its baseline.
04
Timeline
The planned phase of each month, per project. The marked column is the reporting month.
05
Composition
By strategic driver, status, location and current phase; missing values counted as “not set”.
Effort tab · what was consumed
06
By resource
Did each person report what the plan put on them, up to their last reported day?
07
Per project
Is a project consuming its estimate faster than it progresses?
08
Weekly workload
Week by week: projects, business as usual, absence and the rest, against contracted hours.
09
Effort by month
Hours reported each month against each person's contract.
10
Project share
Of all hours reported, how many carried a project code, per team.
The plan, the timeline and the effort panels follow the window. Budget, consumed-against-estimate and the register always count from each project's start.
Reading the colours
Under 80% · spare capacity
80–100% · fully committed
Over 100% · the month does not fit
Empty · nothing entered yet, a gap
The thin stripe at the left of each team's band, in every folded chart: green in order, amber to watch, red to check. The Manager's thresholds set it.
The reliability score
Projects with an effort estimate
20%
Projects with resources allocated
30%
Effort reported for the last complete week
40%
Reported phase on plan
10%
Default weights shown. By default green at 100%, amber from 90%, red below. Weights and bands are set by the Manager.
Portfolio Control Center by BI Development
04 / 07
Contents ↑
Portfolio Control Center · Guest manual
Guest

Project budget, month by month

Only the projects’ costs: the invoices the Team Leads book, against each project’s approved budget. Licences, subscriptions and the overall budget stay outside.

Annual budget, on the board
Figure
Means
Committed
Invoiced, plus the projects’ baselines for the months left in the year.
Free for new projects
The year’s budget minus what is committed. Red when the projects already need more. Projects without an approved budget are named, not counted.
Projects, per month
Invoiced (solid), then what is still to come (hatched): the spikes show month by month.
Each project, against its monthly baseline

Board › 03 Budget › Per month. The approved budget spread evenly from start to go-live: 100k over five months, 20k a month. Red: a month above its baseline. Under the name, the balance: “Invoiced €92,000 of €100,000 · €8,000 left”.

18k / 20kJan15k / 20kFeb20k / 20kMar22k / 20kApr17k / 20kMay
When
The baseline
On hold
The months on hold carry nothing. When the project resumes, what is left is spread over the months up to go-live.
Go-live moved
What is left is spread over the months up to the new go-live.
Go-live passed, not moved
What is left falls on the current month, and the line asks for the new go-live, set in the Team Lead Workspace. Moving it is the Team Lead’s job.
Closed earlier
The months with no activity give their share to the last month with activity: the unused money shows there.
Portfolio Control Center by BI Development
05 / 07
Contents ↑
Portfolio Control Center · Guest manual
The board

The reliability score, worked

The score says how far the data under the board can be trusted. It is about the data, not about how well the projects are going.

A worked example, with the default weights
Check
Result
Pass rate
Weight
Points
Projects with an effort estimate
8 of 10
80%
20%
16.0
Projects with resources allocated
9 of 10
90%
30%
27.0
Effort reported for the last complete week
5 of 6 people
83%
40%
33.3
Reported phase on plan
6 of 9
67%
10%
6.7
Reliability score
83%

83% is below the amber band (90% by default), so the dial is red. The biggest loss is the weekly effort: one person in six has not reported.

Who brings each check up
Check fails because
Fixed by
a project has no effort estimate
the team's Team Lead, in Projects
nobody is allocated to a project this month
the team's Team Lead, in Allocation
a person has not reported last week
the team's Team Lead, by importing the effort
the phase is behind the timeline
the team's Team Lead updates the phase, or the plan is revised
a project has no timeline
the team's Team Lead, in Planned phase, by month
Gaps lower the score on purpose. A project with no data still counts in every check. Nothing is left out of the count to make the score look better. The one exception is time the data could not cover: a team that came with projects already running owes no week before its monitoring start, and its opening balance stands for that time.
Portfolio Control Center by BI Development
06 / 07
Contents ↑
Portfolio Control Center · Guest manual
Reference

Quick reference

Terms
FTE
Share of a full-time contract: 1.00 full time, 0.50 half. Capacity is always written in FTE.
BAU
Business as usual: the part of the FTE that runs the business.
Net capacity
FTE minus BAU: what is left for projects.
Allocation
Share of a month planned on a project, in percent. 100% = one person full time, one month.
FTE-month
One person full time for one month. Effort estimates are given in it.
Load index
Committed allocation ÷ net capacity, per team and month.
Utilisation
BAU plus allocation ÷ the person's FTE, per month. Above 100% the month does not fit.
Completion
The percentage the project's phase carries. Never typed.
Execution order
One queue across all delivery teams. 1 is worked first.
Reliability score
Weighted result of four checks on the data under the board.
Report
Today's board, published by the Manager. Never changes.
Month photo
The board as of a closed month's last day. Taken when the Manager confirms the month, or by itself at the end of the following month. Never changes.
Closing a month
Each team closes its month, in order; the Manager confirms last. The month's allocation, effort and invoices then no longer change.
Reporting date
The report or month photo the board shows. Each reopens exactly as it was.
Window
The months in view, counted from the reporting date.
Display profile
A named set of colour bands, thresholds, window and board panels. The Manager's default opens for everyone.
Seat
One licence of your plan, for one person. A waiting invitation takes one.
Who to ask
Access, roles, teams, project identity, parameters, reports
the Manager
A team's people, allocation, project details, invoices, effort, its month
that team's Team Lead
A seat or licence
the Manager
Anything about the product
BI Development · support@bidevelopment.ro